19.
The Chashma Right Bank Irrigation Project (CRBIP) is an extensive
irrigation project in Pakistan that involves the construction of a
274 km canal along the Indus River, and the construction of 72 distribution
canals, 68 cross structures and 91 bridges. The main canal off-taking
from the Indus River is a contour channel irrigating areas only on
its left side. It is an inter-provincial irrigation project and physically
located in two districts of Pakistan: Dera Ismail Khan (D.I. Khan)
in North-West Frontier Province (NWFP) and Dera Ghazi Khan (D.G. Khan)
in Punjab Province. The first two stages have already been completed
and irrigate the lands of D.I. Khan.
20.
The current third stage of the CRBIP, which is under implementation,
will irrigate the lands of both D.I.Khan and D.G.Khan districts.
The Chashma Right Bank Canal (CRBC) was initially planned to provide
perennial irrigation to command a cultural area 570,000 acres, which
include 350,000 acres in NWFP Province, and 220,000 acres in Punjab
Province. Later on, the cultivable command area increased to 606,000
acres following the decision of shifting the alignment of main canal
further uphill to the west.
21.
The CRBIP design preparation and implementation history is marred
with significant disruptions, substantial delays and partly failure.
West Pakistan Power and Irrigation Department conducted initial
project investigations in 1960s and assessed the possibility and
scope for providing perennial irrigation supplies to the area lying
above the command of existing inundation canals and beyond the reach
of perennial Zams (hill-torrents) emerging from the Sulaiman range
into the plain of the Dera Ismail Khan and Dera Ghazi Khan district.
The option of bringing a canal on the right bank of the Indus River
from Kalabagh head works was considered. The further work on preparation
of detailed feasibility report was entrusted to Water and Power
Development Authority (WAPDA) in late 1960. Meanwhile, the construction
of a barrage on the Indus River at Chashma as part of the Indus
Basin Project (IBP) made it possible to taking off a canal on the
right bank from the Chashma Barrage.
22. The first feasibility report was prepared by WAPDA in 1970.
The feasibility report proposed the gravity canal system to irrigate
500,000 acres of land: 350,000 acres in the Dera Ismail Khan district
and 150,000 acres in the Dera Ghazi Khan district.
23.
The first feasibility report was revised in 1973. The project revision
led to a dramatic increase in the CRBIP's command area. The revised
report envisaged the irrigation of 1,368,000 acres in the Dera Ismail
Khan and Dera Ghazi Khan districts through gravity and pumping cum
gravity system (*3). It was also decided to exclude drainage component
from the original project plan in order to control the project cost.
A resurrected inter-provincial water dispute following the Indus
Basin Water Treaty remained one of the major determinants of decisions
with regard to the CRBIP design and system capacity. Three provinces-Punjab,
NWFP and Sind, were direct stakeholders in inter-provincial water
sharing arrangements.
24.
The Bank's involvement in the CRBIP started in 1976 when a fact-finding
mission visited the proposed site of the project in D.I.Khan district.
The mission asked for further information and handed over a questionnaire
to WAPDA. A supplementary questionnaire was also provided to WAPDA
during the re-appraisal mission. The third and final appraisal mission
came in August 1977, and a Memorandum of Understanding (MOU) was
signed to fund the project (Phase-I Gravity Flow System) at the
end of the mission visit. The project loan totaling $31.5 million
was approved on 15th December 1977. The project (Phase-I Gravity
Flow System) was then meant to irrigate 202,350 hectares in both
the NWFP and Punjab Province (*4).
25.
By late 1979, the project work virtually ceased due to the substantial
cost overrun. The revised PC-1 Proforma prepared by WAPDA assessed
more than two time increase in the project cost. This situation
led the government to impose ban on the award of new contract. Subsequently,
the Bank suspended the loan disbursement pending resolution of the
cost overrun issue. Management justified the decision of loan suspension
and pleaded that the appraisal was conducted without its involvement
in project preparation and it relied heavily on WAPDA's original
proposal (*5). While WAPDA argued that such substantial cost overrun
occurred due to the lack of detailed project planning and field
surveys (*6).
26.
As a result, the Government and WAPDA underwent a lengthy project
reformulation exercise. A high level technical committee that was
mandated to review the revised costs and suggest cost reduction
measures was constituted by the government in February 1980. The
high level technical committee directed WAPDA to prepare cost estimates
for various alternatives rowed-kohi (hill-torrent irrigation) schemes
in the project area during its last meeting held on 1st May 1980.
Meanwhile, it was decided to engage NESPAK-an engineering consultant
firm- for review of the design, cost estimates and economics of
the CRBIP. NESPAK submitted three plans including revised plan of
the project as contained in the revised PC-Proforma of 1979, alternative
plan and cost reduction plan. The recommendation was made in the
favor of alternative plan. On 11th December 1980, the Federal Ministry
of Water and Power directed WAPDA to carry out the study on cross-drainage
works and rowed-kohi (hill-torrent irrigation) scheme to ensure
minimum cross-drainage works and maximum spreading and utilization
of floodwater of hill-torrents as part of the CRBIP. However, WAPDA
rejected this idea as well and claimed that rowed-kohi (hill-torrent
irrigation) development scheme would not be economically attractive.
It was also argued that the decrease in number of cross-drainage
works would not necessarily result in reduction of the project cost
(*7). Rather, WAPDA maintained that its suggested lift scheme starting
from remodeled head regulator to the tail end along with a parallel
channel was technically and financially most viable project design.
The issue was finally resolved in a high level meeting chaired by
the then finance minister. A gravity flow canal design with a capacity
of 4879 cusecs was recommended. It was also decided to design and
implement the project in three stages spread over 10 years (*8).
27.
Meanwhile, the Government requested technical assistance from the
Bank in 1981. The technical assistance (*9) reviewed and reassessed
the reformulated and staged CRBIP. Following review of the Consultant's
report and negotiations between the Government and the Bank, a revised
CRBIP was proposed in 1984, with a total investment cost of $577
million consisting of $377 million for the main canal system, including
cross drainage structures for the main canal system and $200 million
for command area development (CAD), inclusive of surface and sub-surface
drainage and watercourses construction (*10). The rehabilitation
of Paharpur canal was also included in the CRBIP Stage I. The Bank
formally consented to proceed with the Stage I and immediately reactivated
the suspended loan. Thus the already separately approved loan of
$25 million for on On-farm Water Management Project (OFWMP) (*11)
, aimed to improve the water availability at the farm level in the
existing irrigated area previously served by the Paharpur canal,
became linked with the overall CRBIP. In the same year, the Bank
also approved a separate loan of $40 million for the development
of Chashma command area (*12). The CRBIP Stage-I was completed in
December 1986.
28.
The total CRBIP-Stage I command area consists of 140,000 acres,
of which only 14,000 ha were newly irrigated area. Even there was
also some partial tubewell irrigation in the new canal command area.
The remaining command area was already being irrigated by the perennial
water supplies from Paharpur system in Dera Ismail Khan District.
The Project Performance Audit Report (PPAR) on the Chashma Command
Area Development Project points out that the benefits in the CRBIP
Stage 1 have been underachieved. It identifies that projections
of future-without-project (FWOP) cropping intensities and yields
in the Paharpur command area were based on the 1960s estimates in
WAPDA's 1970 feasibility report. Subsequent revisions substantially
lagged improvements. Projection of the FWOP situation ignored increases
in cropping intensity and yields that could have been predicted
to follow the commissioning of the Chashma Barrage and the consequent
conversion of the Paharpur system from an inundation system to a
perennial system prior to the commencement of CRBIP Stage 1. The
PPAR concludes that these developments would have raised cropping
intensities to about 100 percent by FY 1986 without the project.
It further notes that the CRBIP Stage 1, in fact, suffered large
seepage losses that caused water logging and reduced cropping intensities
in the first few years of canal operations. Department of Agriculture
informed the Post- Evaluation Mission (PEM) that the waterlogged
area has been increasing since 1995 and now affects some 4,000 ha
(*13). A special study in preparation for the PEM for the CRBIP
and OFWMP was conducted in late 1990. The report says that locals
feel that as the Paharpur canal already irrigated the area, they
did not suffer from severe water shortages, and the net result of
the project has been more harmful than beneficial (*14). The 1994
Study by the International Water and Irrigation Management Institute
(IWIMI) in Stage I area concluded that more than 20,000-25,000 ha
in lower reaches of CRBIP Stage III would experience acute water
shortages because of prevailing poor irrigation management practices,
high cropping intensities and extensive cultivation of water intensive
crops such as rice and sugarcane (*15).
29.
In December 1987, the Bank approved a loan for $48 million for CRBIP
Stage II (*16). The work on the CRBIP Stage- II commenced in August
1988 and was completed in June 1992. Components common to all three
projects including command area development and drainage, which
covered the Stage I area, have been included in a single package
of components for the full development of the Stage II. The canal
command area (CCA) of CRBIP Stage ll is about 38,000 ha, made up
of 23,900 ha of un-irrigated lands (62 percent), 11,100 ha of tubewell-irrigated
land (30 percent) and 3,000 ha already irrigated from the tail end
of the Pahrapur system (*17).
30.
WAPDA felt it urgent to continue with the momentum gained at the
completion of the Stage 11. The dovetailing work was thus completed
prior to the commencement of CRBIP Stage III (*18). The already
engaged contractors for Stage II through a variation order did this
work. However, the government was not satisfied with the decision
of WAPDA to undertake dovetailing work and termed the award of contract
for dovetailing work on the basis of negotiation highly irregular
and against the prescribed rules. An investigation was also ordered
to investigate the matter. The result of investigation is not known.
31.
Financing for the current and third stage was approved by the ADB
in December 1991 for $185 million, which is about 64% of the total
cost of stage III. The Government of Germany (KFW) has also loaned
about $40 million. The Appraisal Report on the CRBIP Stage III justified
the project on the basis that full potential of the staged development
of the overall CRBIP could not be realized without the completion
of Stage III (*19). The project objectives are to (i) provide a
dependable perennial irrigation supply, (ii) ensure efficient distribution
of water, (iii) provide necessary drainage and flood relief, (iv)
improve access within the area, and (v) strengthen agriculture support
services (*20).
32.
The CRBIP Stage III once again experienced changes in the project
design, cost overrun and substantial delay in the implementation
process. Two important inter-linked changes were made in the approved
design of the CRBIP Stage III. First, it was decided to replace
culverts and siphons with super-passages in cross-drainage works.
This decision was taken despite the fact that super-passages were
more costly than culverts and siphons. It was however envisaged
that super-passages would be economical in the long run (*21). Another
associated change in the project design was made by shifting the
alignment of the main canal further uphill to the west in order
to enable the use of super-passages for the crossing of flood flows
of various hill-torrents (*22). These changes in the project design
later on resulted into serious adverse social and environmental
impact including project-induced displacement.
33.
Despite the rush initially shown by the WAPDA with regard to the
completion of dovetailing work, the implementation of the current
CRBIP Stage III underwent substantial delay. It was envisaged at
the time of appraisal that the construction of the main canal would
start by early 1992. However, the major contract for its construction
(Contract C-65) was not awarded until late 1997. The PC-Proforma
(4th Revision) gives us in-depth insights into the causes and implications
of project delays. It says that the delay happened because the donors
held up their concurrence desiring that 3rd PC-1 1996 should be
first approved by the Economic Evaluation Committee (ECNEC) and
also the tender be awarded to the 2nd lowest M/s TEKSER whose bid
was higher by Rs.180 million from that of the lowest bidder i.e.
M/s China Geo Engg. Corp. WAPDA claims that it tried its best to
convince the Bank for the award of contract to the 1st lowest bidder
so as to save the national exchequer from an extra burden of Rs.180
million, but in vain (*23). Similarly, delay in the award of Contract
No.66 once again occurred due to the reluctance of donors in giving
their concurrence. The tender for the contract were opened on 5th
December 1996 but the concurrence of the donors to sign the contract
agreement was not received till 20th February 1999 (*24). The process
of award for this contract took 27 months against the scheduled
4 months. One of the reasons of delay was the insistence from the
donors to include the provisions of vehicles in the BOQ of the tender
documents. WAPDA was of the view that adequate vehicles were available
from the completed projects to cater to the need of this contract
(*25). Also, two other contracts could not be administered according
to scheduled time because of the demand from the donors to ensure
the availability of counterpart funds and resolution of Operation
and Maintenance (O&M) issue.
34.
Stage II&I of CRBIP were completed by WAPDA without reliance
upon international contractors and consultants. However, the Stage
III is an entirely different story. The Appraisal of CRBIP Stage
III attributed the delays experienced in Stage I & II to the
failure of local contractors, and recommended that civil works for
the construction of main canal, flood carrier channels, and distributaries,
minors and surface drains should be tendered in larger packages
under international competitive bidding (ICB) procedures to attract
large international contractors for the main canal and larger local
and/or international contractors for the distribution system (*26).
Extensive involvement of international consultants was envisaged
in the CRBIP Stage III, in order to undertake further design investigation,
planning and preparation of implementation schedule and contract
administration including the preparation of pre-qualification and
tender documents and bid evaluation. Ironically, despite such extensive
engagement of international consultants in project preparation and
implementation, the project design suffered major faults along with
substantial delays. The consultants also failed to ensure the efficient
and timely administration of contract and thus benefited from this
situation. Payment to the expatriate consultants involved in the
Stage III is being made in foreign currency. Due to the devaluation
of local currency up to the extent of 108 percent against US$ during
this period, the cost overrun in consultancy services is up to Rs.457
million (*27).
35. By April of 1999, there were already substantial delays and
cost overruns and only 15% of the Stage III had been completed.
Instead of requesting a new loan for CRBIP, the Government of Pakistan
proposed that cost overruns be met by utilizing funds from the ADB-funded
National Drainage Sector project. In July 1999, the ADB approved
a transfer of $33.5 million from the latter project to the CRBIP.
Subsequently, the cost overrun estimates were reduced, resulting
in a surplus of $5.1 million that was redirected back to the National
Drainage Project. The total (net) loan amount for the CRBIP Stage
III is now $207.8 million, of which $163.1 million has been disbursed.
The closing date of the loan was originally September 30, 2000,
but it has been extended to December 31, 2002.
|