It
is now almost an established fact of Third World uplift paradigm that
different people view a development project and its impacts from different
angles. So the story of some individuals, trying to bring all concerned
parties to view a project from the same standpoint, can be interesting
as well as informative.
Six men, all
in their individual capacity but with authorisation from the organisations
they work with, are doing just that in Pakistan. The project that
they have focussed on is the third and final phase of a canal system,
called Chashma Right Bank Irrigation Project. The parties they want
to bring round to the point of view of the people affected by the
project are Pakistan's Water and Power Development Authority (Wapda)
and Manila-based Asian Development Bank (ADB).
Their concerns:
to let authorities realise that the project is environmentally hazardous,
economically unviable and socially disruptive, if not altogether
destructive.
Their aim:
to make ADB analyse the impacts of the project and devise effective
mechanisms to redress the problems of the people in the area of
the project. To achieve their goal, they have filed an inspection
claim with the Bank, which was received by its Manila headquarters
in November 2002.
Their problems:
unwillingness to share the information and pertinent documents by
the authorities; hampering their efforts to make their claim legally
acceptable; and a plethora of legalistic impediments which they
need to cross over before their voice is finally heard.
But the question
is whether their efforts mean anything, considering that the project
is already in its last stages. In fact, it was scheduled for completion
by 31st December 2002.
Mushtaq Gadi,
who spearheads the efforts of these people, says that their aim
is to make the Bank understand the reasons for their unacceptable
conduct vis-a-vis the financing of the project and the subsequent
requests for analysing its adverse impacts. This, he says, is all
the more needed so as to prevent their recurrence in other Bank
projects.
As far as the
Chashma Canal project is concerned, Gadi and his cohorts want the
Bank to focus on three major areas in its inspection, if it agrees
to carry out one. First, they want ADB to analyse the defects in
the design of the canal, which is threatening the western side of
the project area with severe flooding. It is causing inundation
of arable land in the eastern side by the water left to flow openly
into the river Indus. Second, they want the people to get adequate
compensation for the loss of their land, livelihood and housing
due to the project. Last but not least, they want the project not
to result in a demographic imbalance against the communities that
are already at a social disadvantage. If it happens, they want some
mechanism to ensure that the people's rights are fully protected.
So, what is
happening to their request for inspection? Takashi Matsuo, a senior
project specialist with ADB's resident mission in Pakistan, says
the Bank has a long and complicated procedure to follow before the
request is finally granted. Matsuo tells that a Board Inspection
Committee of the Bank is currently awaiting a response, which was
due two days ago, from the Bank's management on the request. In
two weeks time, the committee will decide on the response to recommend
whether or not to grant the request.
One may ask,
what is the need to request for the inspection? "The process
of redressing the grievances of the people affected by the project
has been painfully slow," says Gadi. "Whatever realisation
about these grievances exists now among the official circle is the
result of a long wait and a concerted campaign by the effected people,"
he adds.
The project
started in 1991 but it was only in 1994 that Wapda admitted that
the project carries environmental as well as social repercussions.
Apart from this admission, adequate measures to redress these costs
are still lacking. Take, for example, the case of land acquired
for the project. First, it was taken away, violating the law of
the land; and now the process of disbursing compensation is moving
at a snail's pace.
Riaz Ahmad
Khan, federal secretary of Water and Power Ministry, denies that
the acquisition of land for the project violated any law. "We
acquire land, not confiscate it, and that can happen only under
some rules and regulations. If somebody thinks otherwise, it is
his/her opinion, not ours," he asserts. But Matsuo says that
the process of disbursing compensation has taken more than it should
have. "So far only 30% claims for compensations have been settled,
out of 13,442 acres of land acquired for the project in the Punjab.
In the Frontier, however, almost 75% claims have been settled, out
of 6,061 acres of acquired land," he reports.
The figures
he quotes are astonishing if one also takes into account the figures
quoted on 27th January by the Water and Power Ministry. According
to these figures, on 20th January, Rs248,000m have been allocated
as land compensation funds in the Frontier, whereas only 20% of
this money had been disbursed to the landowners by 20th January.
In the Punjab, the figure for the paid compensation by 20th January
goes further down to 10%, according to the document produced by
the Ministry.
Though the
problems persist and are not likely to go away in immediate future,
activists such as Gadi deserve praise for the fact that their efforts
have resulted in the establishment of Institution of Grievance Redress
and Settlement Committee. This committee, according to official
documents, is being set up to find a solution to all the outstanding
problems that have been raised on account of land acquisition, resettlement,
compensation and rehabilitation.
Riaz Ahmad
Khan says that the committee is soon to be given a formal status
through a notification. "It is a comprehensive mechanism to
redress any problem arising out of the project. Anyone effected
in any way can come to the committee and seek compensation for the
damage done to him due to the project," Riaz pledges. But what
about the request for inspection? Riaz says that he sees no justification
for the claim once the committee starts working.
Gadi only partially
agrees with this assessment of the committee's functions. "The
Terms of Reference for the working of the committee clearly state
that it has no authority to implement its recommendations. This
authority lies with Wapda and provincial governments. This duality
of functions is what renders the committee a toothless tool,"
he says. "This still leaves room for us to go ahead with our
request for inspection."
Federal Minister
for Water and Power, Aftab Ahmad Khan Sherpao, tells that every
development project is bound to create some problems. "We need
to assess whether these problems outweigh the utility of the project.
If not, then we should go ahead with the development, and at the
same time creating mechanisms to address problems it creates,"
he says. "Two considerations should lie at the heart of any
development project--people's welfare and a strict adherence to
rules and regulations."
Activists like
Gadi can take heart from the Honourable Minister's words. If, according
to their point of view, the project has violated the rules and regulations
of ADB, as well as the Government of Pakistan, and they are able
to substantiate their claim, then there is no reason why authorities
should not pay heed.
|